Posted on: March 11, 2022[ARCHIVED] Kirk St. Project Update, Fri., 3/11/2022
Base asphalt paving was placed in Phase 3 this week. Dependent on weather, soil stabilization is scheduled for Phase 4 next week. Continued forming & placement of curb/gutter will take place afterwards.